Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-25 05-330714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 19% 05-SLO-46-32.2/37.2 Federal Project: HPLU-6205(10) HP21-6205(12) L-6205(12) Progress payment No. 04 Payment period ending: 06-20-08 PAPICH CONSTRUCTION COMPANY INC P O BOX 2217 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,963,830.77 813,931.95 2.a. Extra Work 52,885.48 5,011.39 b. Adjustment Comp. 3. Materials on Hand 232,064.00 -111,801.83 4. Earned Subject to Retention 2,248,780.25 707,141.51 5. Mobilization 10,000.00 0.00 6. Total Work Completed 2,026,716.25 7. Deductions -112,125.00 -35,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,146,655.25 672,141.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 672,141.51