Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-14-42 05-330714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-46-32.2/37.2 Federal Project: HPLU-6205(10) HP21-6205(12) L-6205(12) Progress payment No. 31 Payment period ending: 08-20-10 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,472,287.01 2,555,112.74 2.a. Extra Work 808,007.38 26,894.62 b. Adjustment Comp. 263,999.88 -23,311.22 3. Materials on Hand 273,090.00 -76,483.00 4. Earned Subject to Retention 24,817,384.27 2,482,213.14 5. Mobilization 20,000.00 0.00 6. Total Work Completed 24,564,294.27 7. Deductions -163,685.00 -16,310.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,673,699.27 2,465,903.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,465,903.14