Dept. of Trans. PROGRESS Serial No. Contract No. 10-293-15-35 05-330714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-46-32.2/37.2 Federal Project: HPLU-6205(10) HP21-6205(12) L-6205(12) Progress payment No. 33 Payment period ending: 10-20-10 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,454,585.57 807,865.02 2.a. Extra Work 875,614.52 58,766.70 b. Adjustment Comp. 243,999.24 -20,000.64 3. Materials on Hand 69,304.00 -103,775.00 4. Earned Subject to Retention 27,643,503.33 742,856.08 5. Mobilization 20,000.00 0.00 6. Total Work Completed 27,594,199.33 7. Deductions -163,685.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,499,818.33 742,856.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 742,856.08