Dept. of Trans. PROGRESS Serial No. Contract No. 14-022-13-25 05-330724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 86% 05-SLO-46-36.6/41.2 Federal Project: ACST-P046(43) PE-P046(43) HPLU-6205(15) Progress payment No. 37 Payment period ending: 01-20-14 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,609,413.44 330,473.05 2.a. Extra Work 1,458,610.14 61,761.33 b. Adjustment Comp. 1,622,048.93 0.00 3. Materials on Hand 93,228.00 -1,410.00 4. Earned Subject to Retention 41,783,300.51 390,824.38 5. Mobilization 2,203,694.20 0.00 6. Total Work Completed 43,893,766.71 7. Deductions -128,928.60 -98,768.60 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,858,066.11 292,055.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 292,055.78