Dept. of Trans. PROGRESS Serial No. Contract No. 11-297-11-05 05-330744 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 70% 05-SLO-46-32.1/36.7 Federal Project: NH-P046(46) Progress payment No. 03 Payment period ending: 10-20-11 ELITE LANDSCAPING INC 2972 LARKIN AVENUE CLOVIS CA 93612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 133,524.10 77,566.60 2.a. Extra Work 648.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 134,172.10 77,566.60 5. Mobilization 23,750.00 5,000.00 6. Total Work Completed 157,922.10 7. Deductions -4,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 153,922.10 80,566.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,566.60