Dept. of Trans. PROGRESS Serial No. Contract No. 13-112-10-58 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 24% 05-SLO-46-40.7/46.3 Federal Project: NONE Progress payment No. 10 Payment period ending: 04-20-13 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,249,523.39 627,165.09 2.a. Extra Work 107,171.43 38,191.05 b. Adjustment Comp. 15,986.74 0.00 3. Materials on Hand 295,701.00 20,010.00 4. Earned Subject to Retention 5,668,382.56 685,366.14 5. Mobilization 34,382.17 0.00 6. Total Work Completed 5,407,063.73 7. Deductions -710.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,702,054.73 685,366.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 685,366.14