Dept. of Trans. PROGRESS Serial No. Contract No. 13-295-14-08 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 49% 05-SLO-46-40.7/46.3 Federal Project: NONE Progress payment No. 16 Payment period ending: 10-20-13 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,899,714.22 595,075.37 2.a. Extra Work 622,135.81 196,640.72 b. Adjustment Comp. 87,406.97 10,196.34 3. Materials on Hand 252,468.00 -1,817.00 4. Earned Subject to Retention 8,861,725.00 800,095.43 5. Mobilization 43,550.75 0.00 6. Total Work Completed 8,652,807.75 7. Deductions -66,027.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,839,248.25 800,095.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 800,095.43