Dept. of Trans. PROGRESS Serial No. Contract No. 14-108-09-44 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 62% 05-SLO-46-40.7/46.3 Federal Project: NONE Progress payment No. 22 Payment period ending: 04-20-14 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,571,333.06 638,117.78 2.a. Extra Work 901,905.40 13,782.54 b. Adjustment Comp. 143,597.31 0.00 3. Materials on Hand 256,852.00 -43,790.00 4. Earned Subject to Retention 12,873,687.77 608,110.32 5. Mobilization 43,550.75 0.00 6. Total Work Completed 12,660,386.52 7. Deductions -12,695.00 91,598.34 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,904,543.52 699,708.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 699,708.66