Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-17-37 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 85% Location: Federal Project: 05-SLO-46-40.7/46.3 NONE Progress payment No. 036 Payment period ending: 05-20-15 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,815,218.62 1,582,542.62 2. a. Extra Work 1,574,046.40 73,534.91 b. Adustment Comp. 546,463.62 65,987.43 3. Materials on Hand 185,732.00 -11,207.00 4. Earned Subject to Retention 26,121,460.64 1,710,857.96 5. Mobilization 45,842.89 0.00 6. Total Work Completed 25,981,571.53 7. Deductions -6,658.00 -963.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,160,645.53 1,709,894.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,709,894.96