Dept. of Trans. PROGRESS Serial No. Contract No. 15-203-11-27 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 92% Location: Federal Project: 05-SLO-46-40.7/46.3 NONE Progress payment No. 038 Payment period ending: 07-20-15 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,754,061.11 1,835,128.23 2. a. Extra Work 1,909,820.95 135,384.03 b. Adustment Comp. 623,513.45 19,571.58 3. Materials on Hand 172,481.21 -23,429.89 4. Earned Subject to Retention 29,459,876.72 1,966,653.95 5. Mobilization 45,842.89 0.00 6. Total Work Completed 29,333,238.40 7. Deductions -9,804.25 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,495,915.36 1,966,653.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,966,653.95