Dept. of Trans. PROGRESS Serial No. Contract No. 15-299-15-29 05-330774 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 97% Location: Federal Project: 05-SLO-46-40.7/46.3 NONE Progress payment No. 042 Payment period ending: 10-20-15 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH, CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,111,368.46 975,254.30 2. a. Extra Work 2,176,662.29 7,800.33 b. Adustment Comp. 578,551.32 14,158.14 3. Materials on Hand 150,855.00 -2,212.00 4. Earned Subject to Retention 33,017,437.07 995,000.77 5. Mobilization 45,842.89 0.00 6. Total Work Completed 32,912,424.96 7. Deductions -15,804.25 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,047,475.71 992,000.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 992,000.77