Dept. of Trans. PROGRESS Serial No. Contract No. 19-017-10-07 05-330784 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 88% Location: Federal Project: 05-SLO-46-46.0/50.2 NONE Progress payment No. 035 Payment period ending: 01-20-19 BROSAMER & WALL INC 1777 OAKLAND BLVD # #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,306,634.64 73,913.30 2. a. Extra Work 2,315,309.45 42,376.55 b. Adustment Comp. 346,460.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 39,968,404.23 116,289.85 5. Mobilization 4,100,097.54 0.00 6. Total Work Completed 44,068,501.77 7. Deductions -128,326.36 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,940,175.41 124,289.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 124,289.85