Dept. of Trans. PROGRESS Serial No. Contract No. 22-171-13-38 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 13% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 003 Payment period ending: 06-20-22 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,364,299.45 4,997,354.43 2. a. Extra Work 2,929.66 2,929.66 b. Adustment Comp. 3. Materials on Hand 730,265.00 -20,076.00 4. Earned Subject to Retention 18,097,494.11 4,980,208.09 5. Mobilization 8,716,500.00 0.00 6. Total Work Completed 26,083,729.11 7. Deductions -12,683.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,801,310.51 4,980,208.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,980,208.09