Dept. of Trans. PROGRESS Serial No. Contract No. 22-300-08-33 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 28% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 007 Payment period ending: 10-20-22 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,184,931.42 3,889,112.84 2. a. Extra Work 220,415.84 17,695.03 b. Adustment Comp. 79,318.13 0.00 3. Materials on Hand 592,194.81 288,078.76 4. Earned Subject to Retention 35,076,860.20 4,194,886.63 5. Mobilization 11,040,900.00 0.00 6. Total Work Completed 45,525,565.39 7. Deductions -37,572.96 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,080,187.24 4,184,886.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,184,886.63