Dept. of Trans. PROGRESS Serial No. Contract No. 24-086-20-34 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 69% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 026 Payment period ending: 03-20-24 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,353,756.69 872,756.04 2. a. Extra Work 878,241.21 153,843.42 b. Adustment Comp. 90,811.14 -1,946.11 3. Materials on Hand 684,110.49 155,589.96 4. Earned Subject to Retention 74,006,919.53 1,180,243.31 5. Mobilization 11,622,000.00 0.00 6. Total Work Completed 84,944,809.04 7. Deductions -116,745.65 -17,096.70 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 85,512,173.88 1,163,146.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,163,146.61