Dept. of Trans. PROGRESS Serial No. Contract No. 24-323-19-20 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 91% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 034 Payment period ending: 11-20-24 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 95,967,541.73 4,021,725.70 2. a. Extra Work 1,335,675.85 66,006.29 b. Adustment Comp. 89,399.29 0.00 3. Materials on Hand 199,253.82 74,564.94 4. Earned Subject to Retention 97,591,870.69 4,162,296.93 5. Mobilization 11,622,000.00 0.00 6. Total Work Completed 109,014,616.87 7. Deductions -369,973.12 2,990.94 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 108,843,897.57 4,165,287.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,165,287.87