Dept. of Trans. PROGRESS Serial No. Contract No. 24-358-13-30 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 95% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 035 Payment period ending: 12-20-24 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 98,616,527.73 2,648,986.01 2. a. Extra Work 1,340,407.87 4,732.02 b. Adustment Comp. 76,689.50 -12,709.79 3. Materials on Hand 0.00 -199,253.82 4. Earned Subject to Retention 100,033,625.10 2,441,754.42 5. Mobilization 11,622,000.00 0.00 6. Total Work Completed 111,655,625.10 7. Deductions -379,973.12 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 111,275,651.98 2,431,754.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,431,754.42