Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-246-13-09 05-3307A4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-46-49.7/54.7 ACNH-P046(62) Progress payment No. 042 Payment period ending: 05-08-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 102,120,471.02 33,250.00 2. a. Extra Work 2,976,885.94 44,338.05 b. Adustment Comp. -247,535.35 2,284.00 3. Materials on Hand 4. Earned Subject to Retention 104,849,821.61 79,872.05 5. Mobilization 11,622,000.00 0.00 6. Total Work Completed 116,471,821.61 7. Deductions -593,676.19 94,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 115,878,145.42 173,872.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,872.05