Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-13-58 05-3307C4 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 32% Location: Federal Project: 05-SLO-41-44.5/45.3 NONE 05-SLO-46-54.0/57.8 Progress payment No. 024 Payment period ending: 02-20-25 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,545,780.80 3,634,706.72 2. a. Extra Work 965,019.80 12,736.28 b. Adustment Comp. 3. Materials on Hand 859,644.60 0.00 4. Earned Subject to Retention 80,370,445.20 3,647,443.00 5. Mobilization 14,830,182.16 0.00 6. Total Work Completed 94,340,982.76 7. Deductions -923,438.30 -874,711.13 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,277,189.06 2,772,731.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,772,731.87