Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-09-41 05-3307C4 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 36% Location: Federal Project: 05-SLO-41-44.5/45.3 NONE 05-SLO-46-54.0/57.8 Progress payment No. 028 Payment period ending: 06-20-25 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,915,167.38 4,859,956.76 2. a. Extra Work 1,637,424.21 362,526.20 b. Adustment Comp. 3. Materials on Hand 786,979.60 -72,665.00 4. Earned Subject to Retention 100,339,571.19 5,149,817.96 5. Mobilization 14,830,182.16 0.00 6. Total Work Completed 114,382,773.75 7. Deductions -1,330,786.39 87,508.05 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 113,838,966.96 5,237,326.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,237,326.01