Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-11-07 05-3307C4 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 41% Location: Federal Project: 05-SLO-41-44.5/45.3 NONE 05-SLO-46-54.0/57.8 Progress payment No. 030 Payment period ending: 08-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,305,869.55 4,525,979.18 2. a. Extra Work 1,755,630.53 34,642.37 b. Adustment Comp. 3. Materials on Hand 711,488.97 26,202.81 4. Earned Subject to Retention 109,772,989.05 4,586,824.36 5. Mobilization 14,830,182.16 0.00 6. Total Work Completed 123,891,682.24 7. Deductions -1,228,211.93 113,494.46 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 123,374,959.28 4,700,318.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,700,318.82