Dept. of Trans. PROGRESS Serial No. Contract No. 24-355-12-28 05-344904 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 83% Location: Federal Project: 05-SBT-156-3.0/8.2 ACNH-P156(24) HIPL-6205(29) Progress payment No. 028 Payment period ending: 12-18-24 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,455,650.38 22,847.72 2. a. Extra Work 9,065,312.06 215,499.89 b. Adustment Comp. 3. Materials on Hand 668,718.25 38,174.51 4. Earned Subject to Retention 61,189,680.69 276,522.12 5. Mobilization 6,500,000.00 0.00 6. Total Work Completed 67,020,962.44 7. Deductions -70,422.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,619,258.69 276,522.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,522.12