Dept. of Trans. PROGRESS Serial No. Contract No. 01-081-10-38 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 62% 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 08 Payment period ending: 03-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,775,693.48 37,680.00 2.a. Extra Work 54,356.87 21,633.47 b. Adjustment Comp. -2,250.00 -2,250.00 3. Materials on Hand 4. Earned Subject to Retention 1,827,800.35 57,063.47 5. Mobilization 6. Total Work Completed 1,827,800.35 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -91,390.02 -2,853.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,726,410.33 54,210.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,210.29