Dept. of Trans. PROGRESS Serial No. Contract No. 01-110-15-07 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 69% 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 09 Payment period ending: 04-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,144,382.04 368,688.56 2.a. Extra Work 89,790.72 35,433.85 b. Adjustment Comp. -2,250.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,231,922.76 404,122.41 5. Mobilization 6. Total Work Completed 2,231,922.76 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -111,596.14 -20,206.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,110,326.62 383,916.29 10. Reduction Amt to Escrow 11. Payment to Escrow 111,590.00 12. Net Pymt. this Estimate 383,916.29