Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-10-22 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 91% 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 11 Payment period ending: 06-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,794,959.22 460,831.64 2.a. Extra Work 89,790.72 0.00 b. Adjustment Comp. -6,338.14 -4,088.14 3. Materials on Hand 4. Earned Subject to Retention 2,878,411.80 456,743.50 5. Mobilization 6. Total Work Completed 2,878,411.80 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -143,920.59 -22,837.17 b. Unsatisfactory Prog. -32,324.45 -22,837.18 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,682,166.76 401,069.15 10. Reduction Amt to Escrow 11. Payment to Escrow 125,000.00 12. Net Pymt. this Estimate 401,069.15