Dept. of Trans. PROGRESS Serial No. Contract No. 01-267-11-08 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 15 Payment period ending: 09-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,405,620.05 3,234.80 2.a. Extra Work 489,422.49 264,338.34 b. Adjustment Comp. -6,338.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,888,704.40 267,573.14 5. Mobilization 6. Total Work Completed 3,888,704.40 7. Deductions -31,000.00 -1,000.00 8. a.Contract Retentions -194,435.22 -13,378.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,663,269.18 253,194.48 10. Reduction Amt to Escrow 11. Payment to Escrow 125,000.00 12. Net Pymt. this Estimate 253,194.48