Dept. of Trans. PROGRESS Serial No. Contract No. 01-330-12-33 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 17 Payment period ending: 11-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,409,917.10 1,877.85 2.a. Extra Work 498,981.23 3,692.82 b. Adjustment Comp. -6,338.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,902,560.19 5,570.67 5. Mobilization 6. Total Work Completed 3,902,560.19 7. Deductions -20,000.00 11,000.00 8. a.Contract Retentions -195,128.01 -278.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,687,432.18 16,292.14 10. Reduction Amt to Escrow 11. Payment to Escrow 195,120.00 12. Net Pymt. this Estimate 16,292.14