Dept. of Trans. PROGRESS Serial No. Contract No. 01-358-11-12 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 18 Payment period ending: 12-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,411,586.30 1,669.20 2.a. Extra Work 499,987.20 1,005.97 b. Adjustment Comp. -6,338.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,905,235.36 2,675.17 5. Mobilization 6. Total Work Completed 3,905,235.36 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -195,261.77 -133.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,699,973.59 12,541.41 10. Reduction Amt to Escrow 11. Payment to Escrow 195,120.00 12. Net Pymt. this Estimate 12,541.41