Dept. of Trans. SEMI-FINAL Serial No. Contract No. 02-298-09-58 05-348804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SB-154-17.9/21.4 Federal Project: ACST-P154(16) P-P154(16) Progress payment No. 28 Payment period ending: 08-30-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01645 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,425,565.85 0.00 2.a. Extra Work 562,208.46 0.00 b. Adjustment Comp. -20,018.67 -13,680.53 3. Materials on Hand 4. Earned Subject to Retention 3,967,755.64 -13,680.53 5. Mobilization 6. Total Work Completed 3,967,755.64 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -198,986.98 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 198,986.98 0.00 9. Total pay to Contractor 3,967,755.64 -3,680.53 10. Reduction Amt to Escrow -198,690.00 0.00 11. Payment to Escrow 198,690.00 12. Net Pymt. this Estimate -3,680.53