Dept. of Trans. PROGRESS Serial No. Contract No. 02-325-10-19 05-363324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 86% 05-SB-101-R15.2/ .0 Federal Project: ACNH-P101(925) Progress payment No. 05 Payment period ending: 11-20-02 C A RASMUSSEN INC 2360 SHASTA WAY SIMI VALLEY CA 93065 Escrow No. 01952 Total Estimate This Estimate 1. Contract Itms Without Mobil. 204,659.00 14,611.50 2.a. Extra Work 19,735.42 11,014.64 b. Adjustment Comp. -1,600.00 -1,600.00 3. Materials on Hand 109,500.00 0.00 4. Earned Subject to Retention 332,294.42 24,026.14 5. Mobilization 187,500.00 0.00 6. Total Work Completed 410,294.42 7. Deductions 8. a.Contract Retentions -33,229.44 -2,402.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 486,564.98 21,623.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,623.53