Dept. of Trans. PROGRESS Serial No. Contract No. 03-052-10-58 05-363324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 69% 05-SB-101-R15.2/ .0 Federal Project: ACNH-P101(925) Progress payment No. 08 Payment period ending: 02-20-03 C A RASMUSSEN INC 2360 SHASTA WAY SIMI VALLEY CA 93065 Escrow No. 01952 Total Estimate This Estimate 1. Contract Itms Without Mobil. 623,718.05 326,027.05 2.a. Extra Work 67,417.67 45,889.08 b. Adjustment Comp. -3,500.00 -1,900.00 3. Materials on Hand 61,059.00 -48,441.00 4. Earned Subject to Retention 748,694.72 321,575.13 5. Mobilization 237,500.00 50,000.00 6. Total Work Completed 925,135.72 7. Deductions 8. a.Contract Retentions -54,521.82 -11,809.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 931,672.90 359,765.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,765.27