Dept. of Trans. PROGRESS Serial No. Contract No. 09-203-12-24 05-402804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 55% 05-SLO-101-45.2/45.7 Federal Project: 05-SLO-41-15.8/16.0 NONE Progress payment No. 21 Payment period ending: 07-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 02364 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,667,696.58 936,022.22 2.a. Extra Work 421,044.70 8,299.92 b. Adjustment Comp. 218,728.19 0.00 3. Materials on Hand 80,892.53 56,283.50 4. Earned Subject to Retention 9,388,362.00 1,000,605.64 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 10,807,469.47 7. Deductions -17,529.25 -10,885.20 8. a.Contract Retentions -469,418.10 -50,030.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,401,414.65 939,690.16 10. Reduction Amt to Escrow 11. Payment to Escrow 469,410.00 12. Net Pymt. this Estimate 939,690.16