Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-15-25 05-402804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 79% 05-SLO-101-45.2/45.7 Federal Project: 05-SLO-41-15.8/16.0 NONE Progress payment No. 30 Payment period ending: 04-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 02364 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,039,583.55 236,059.53 2.a. Extra Work 503,190.94 6,461.60 b. Adjustment Comp. 226,707.90 1,697.76 3. Materials on Hand 65,253.51 0.00 4. Earned Subject to Retention 12,834,735.90 244,218.89 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 14,269,482.39 7. Deductions -7,895.01 0.00 8. a.Contract Retentions -641,736.80 -12,210.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,685,104.09 232,007.94 10. Reduction Amt to Escrow 11. Payment to Escrow 641,730.00 12. Net Pymt. this Estimate 232,007.94