Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-221-14-02 05-430604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 15% 05-SCR-1-R4.9/17.4 Federal Project: 05-SCR-17-0.3/6.1 NONE Progress payment No. 01 Payment period ending: 08-07-08 T D S ENGINEERING 2899 AGOURA ROAD SUITE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 281,764.45 281,764.45 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 281,764.45 281,764.45 5. Mobilization 66,500.00 66,500.00 6. Total Work Completed 348,264.45 7. Deductions 8. a.Contract Retentions -26,696.94 -26,696.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 321,567.51 321,567.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 321,567.51