Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-056-13-17 05-430604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-1-R4.9/17.4 Federal Project: 05-SCR-17-0.3/6.1 NONE Progress payment No. 08 Payment period ending: 01-29-09 T D S ENGINEERING 1014 S WESTLAKE BLVD, #14-136 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,304,813.66 1,450.00 2.a. Extra Work 50,010.06 14,175.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,354,823.72 15,625.67 5. Mobilization 70,000.00 0.00 6. Total Work Completed 1,424,823.72 7. Deductions -5,000.00 10,000.00 8. a.Contract Retentions -66,228.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 66,228.05 0.00 9. Total pay to Contractor 1,419,823.72 25,625.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,625.67