Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-25 05-441604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 76% 05-SB-192-5.7/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-13-08 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 436,294.80 229,062.80 2.a. Extra Work 64,672.28 14,909.64 b. Adjustment Comp. 54,700.00 54,700.00 3. Materials on Hand 4. Earned Subject to Retention 555,667.08 298,672.44 5. Mobilization 25,000.00 1,250.00 6. Total Work Completed 580,667.08 7. Deductions -17,698.47 -17,698.47 8. a.Contract Retentions -27,783.35 -14,933.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 535,185.26 267,290.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 267,290.35