Dept. of Trans. PROGRESS Serial No. Contract No. 05-115-07-41 05-445004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 9% 05-SLO-1-8.4/8.5 Federal Project: ACST-P001(509) PH-P001(509) Progress payment No. 04 Payment period ending: 04-20-05 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 71,900.70 67,040.70 2.a. Extra Work 7,516.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 79,416.70 67,040.70 5. Mobilization 6. Total Work Completed 79,416.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 79,416.70 67,040.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,040.70