Dept. of Trans. PROGRESS Serial No. Contract No. 08-056-10-16 05-446014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 58% 05-SB-101-84.1/90.9 Federal Project: ACNH-Q101(28) Progress payment No. 20 Payment period ending: 02-20-08 DIABLO CONTRACTORS INC 7 CROW CANYON COURT SUITE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,044,568.88 529,264.88 2.a. Extra Work 199,890.97 -897.79 b. Adjustment Comp. -145,032.82 5,069.00 3. Materials on Hand 4. Earned Subject to Retention 17,099,427.03 533,436.09 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 19,999,427.03 7. Deductions -144,998.72 -132,318.72 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,854,428.31 401,117.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 401,117.37