Dept. of Trans. PROGRESS Serial No. Contract No. 08-113-13-31 05-446014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 62% 05-SB-101-84.1/90.9 Federal Project: ACNH-Q101(28) Progress payment No. 22 Payment period ending: 04-20-08 DIABLO CONTRACTORS INC 7 CROW CANYON COURT SUITE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,737,687.90 856,250.87 2.a. Extra Work 208,521.15 4,224.01 b. Adjustment Comp. -189,946.96 -44,914.14 3. Materials on Hand 4. Earned Subject to Retention 18,756,262.09 815,560.74 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 21,656,262.09 7. Deductions -31,074.28 38,750.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,625,187.81 854,310.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 854,310.74