Dept. of Trans. PROGRESS Serial No. Contract No. 09-203-10-20 05-447804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 58% 05-SB-101-10.8/12.8 Federal Project: NONE Progress payment No. 14 Payment period ending: 07-20-09 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02395 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,337,477.65 1,813,961.49 2.a. Extra Work 268,560.77 23,207.92 b. Adjustment Comp. 822,818.37 17,706.60 3. Materials on Hand 1,069,600.60 458,786.00 4. Earned Subject to Retention 17,498,457.39 2,313,662.01 5. Mobilization 2,612,500.00 0.00 6. Total Work Completed 19,041,356.79 7. Deductions -11,298.16 -10,000.00 8. a.Contract Retentions -878,523.92 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,221,135.31 2,303,662.01 10. Reduction Amt to Escrow 11. Payment to Escrow 878,520.00 12. Net Pymt. this Estimate 2,303,662.01