Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-13-25 05-447804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 64% 05-SB-101-10.8/12.8 Federal Project: NONE Progress payment No. 15 Payment period ending: 08-20-09 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02395 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,608,810.67 1,271,333.02 2.a. Extra Work 256,575.59 -11,985.18 b. Adjustment Comp. 877,080.91 54,262.54 3. Materials on Hand 1,035,955.40 -33,645.20 4. Earned Subject to Retention 18,778,422.57 1,279,965.18 5. Mobilization 2,612,500.00 0.00 6. Total Work Completed 20,354,967.17 7. Deductions -11,298.16 0.00 8. a.Contract Retentions -938,921.13 -60,397.21 b. Unsatisfactory Prog. -63,998.26 -63,998.26 c. Reduction after 95% Comp. 9. Total pay to Contractor 20,376,705.02 1,155,569.71 10. Reduction Amt to Escrow 11. Payment to Escrow 938,920.00 12. Net Pymt. this Estimate 1,155,569.71