Dept. of Trans. PROGRESS Serial No. Contract No. 11-171-13-02 05-447804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 78% 05-SB-101-10.8/12.8 Federal Project: NONE Progress payment No. 38 Payment period ending: 06-20-11 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02395 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,426,200.14 529,081.24 2.a. Extra Work 2,667,378.98 169,172.29 b. Adjustment Comp. 2,205,112.36 -39,335.62 3. Materials on Hand 48,046.30 0.00 4. Earned Subject to Retention 44,346,737.78 658,917.91 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 47,048,691.48 7. Deductions -1,402.70 0.00 8. a.Contract Retentions -2,217,336.89 -32,945.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,877,998.19 625,972.01 10. Reduction Amt to Escrow 11. Payment to Escrow 2,217,330.00 12. Net Pymt. this Estimate 625,972.01