Dept. of Trans. PROGRESS Serial No. Contract No. 12-053-14-15 05-447804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 96% 05-SB-101-10.8/12.8 Federal Project: NONE Progress payment No. 47 Payment period ending: 02-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02395 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,175,443.85 382,815.00 2.a. Extra Work 3,887,949.92 280,179.40 b. Adjustment Comp. 3,039,127.49 -69,937.30 3. Materials on Hand 0.00 -7,223.16 4. Earned Subject to Retention 52,102,521.26 585,833.94 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 54,852,521.26 7. Deductions -6,316.20 6,500.00 8. a.Contract Retentions -2,605,126.06 -29,291.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,241,079.00 563,042.25 10. Reduction Amt to Escrow 11. Payment to Escrow 2,605,120.00 12. Net Pymt. this Estimate 563,042.25