Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-10-02 05-447804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 98% 05-SB-101-10.8/12.8 Federal Project: NONE Progress payment No. 48 Payment period ending: 03-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02395 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,305,731.18 130,287.33 2.a. Extra Work 4,154,304.40 266,354.48 b. Adjustment Comp. 3,035,976.00 -3,151.49 3. Materials on Hand 4. Earned Subject to Retention 52,496,011.58 393,490.32 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 55,246,011.58 7. Deductions -7,816.20 -1,500.00 8. a.Contract Retentions -2,624,800.58 -19,674.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,613,394.80 372,315.80 10. Reduction Amt to Escrow 11. Payment to Escrow 2,624,800.00 12. Net Pymt. this Estimate 372,315.80