Dept. of Trans. PROGRESS Serial No. Contract No. 06-115-11-06 05-448104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 4% 05-SB-101-R8.1/8.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 04-20-06 MENDEZ CONCRETE INC 1210 E SANTA PAULA STREET SANTA PAULA CA 93060 Escrow No. 02210 Total Estimate This Estimate 1. Contract Itms Without Mobil. 433,474.08 340,358.74 2.a. Extra Work 10,920.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 444,394.08 340,358.74 5. Mobilization 166,393.50 166,393.50 6. Total Work Completed 610,787.58 7. Deductions 8. a.Contract Retentions -44,439.41 -34,035.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 566,348.17 472,716.36 10. Reduction Amt to Escrow 11. Payment to Escrow 44,430.00 12. Net Pymt. this Estimate 472,716.36