Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-14-16 05-448104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 28% 05-SB-101-R8.1/8.9 Federal Project: NONE Progress payment No. 06 Payment period ending: 08-20-06 MENDEZ CONCRETE INC 1210 E SANTA PAULA STREET SANTA PAULA CA 93060 Escrow No. 02210 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,881,416.80 425,329.05 2.a. Extra Work 36,582.20 5,419.39 b. Adjustment Comp. 15,312.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,933,311.00 430,748.44 5. Mobilization 316,147.65 0.00 6. Total Work Completed 2,249,458.65 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -96,665.55 -5,845.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,132,793.10 414,902.70 10. Reduction Amt to Escrow 11. Payment to Escrow 96,660.00 12. Net Pymt. this Estimate 414,902.70