Dept. of Trans. PROGRESS Serial No. Contract No. 20-114-19-51 05-448214 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 33% Location: Federal Project: 05-SB-101-2.2/3.3 NONE Progress payment No. 005 Payment period ending: 04-20-20 CENTRAL COAST FINANCIAL GROUP INC 17750 WARDS FERRY RD SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 487,562.88 133,502.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 487,562.88 133,502.00 5. Mobilization 190,000.00 40,000.00 6. Total Work Completed 677,562.88 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 669,562.88 173,502.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,502.00