Dept. of Trans. PROGRESS Serial No. Contract No. 02-080-14-48 05-448314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 25% 05-SB-101-1.0/12.7 Federal Project: ACNH-P101(983) Progress payment No. 04 Payment period ending: 03-20-02 SULLY MILLER CONTRACTING COMPANY 3555 E VINEYARD AVE OXNARD CA 93030 Escrow No. 01873 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,913,602.60 595,803.53 2.a. Extra Work b. Adjustment Comp. 856.00 0.00 3. Materials on Hand 30,403.88 30,403.88 4. Earned Subject to Retention 1,944,862.48 626,207.41 5. Mobilization 6. Total Work Completed 1,914,458.60 7. Deductions -22,000.00 -17,000.00 8. a.Contract Retentions -194,486.25 -62,620.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,728,376.23 546,586.67 10. Reduction Amt to Escrow 11. Payment to Escrow 194,480.00 12. Net Pymt. this Estimate 546,586.67