Dept. of Trans. PROGRESS Serial No. Contract No. 03-328-08-14 05-448314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-101-1.0/12.7 Federal Project: ACNH-P101(983) Progress payment No. 24 Payment period ending: 11-20-03 SULLY MILLER CONTRACTING COMPANY 3555 E VINEYARD AVE OXNARD CA 93030 Escrow No. 01873 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,130,282.95 335,144.55 2.a. Extra Work 1,709,331.35 0.00 b. Adjustment Comp. 288,999.05 -18,612.02 3. Materials on Hand 76,524.67 -77,798.13 4. Earned Subject to Retention 14,205,138.02 238,734.40 5. Mobilization 6. Total Work Completed 14,128,613.35 7. Deductions -72,943.41 0.00 8. a.Contract Retentions -710,256.90 -11,936.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,421,937.71 226,797.68 10. Reduction Amt to Escrow 11. Payment to Escrow 710,250.00 12. Net Pymt. this Estimate 226,797.68