Dept. of Trans. PROGRESS Serial No. Contract No. 01-025-10-04 05-452504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 83% 05-SCR-9-3.9/4.0 Federal Project: ACST-S009(10) P-S009(10) Progress payment No. 08 Payment period ending: 01-20-01 PARNUM PAVING, INC. ASSIGNOR: C A RASMUSSEN, INC. 1324 SOUTH STATE STREET UKIAH, CA 95482 Escrow No. 01366 Total Estimate This Estimate 1. Contract Itms Without Mobil. 646,585.00 76,391.60 2.a. Extra Work 18,775.48 0.00 b. Adjustment Comp. 3. Materials on Hand 33,681.34 -27,608.65 4. Earned Subject to Retention 699,041.82 48,782.95 5. Mobilization 137,000.00 6,850.00 6. Total Work Completed 802,360.48 7. Deductions 8. a.Contract Retentions -34,952.09 -2,439.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 801,089.73 53,193.80 10. Reduction Amt to Escrow 11. Payment to Escrow 34,950.00 12. Net Pymt. this Estimate 53,193.80